By Dominic Mathew, Transportation Policy & Strategy Manager, SAFE’s Coalition for Reimagined Mobility, and Paul Ruiz, Senior Director, Policy
U.S. electricity demand is projected to surge 35–50% by 2040, yet building new grid connections takes up to a decade, with projects completed in 2025 requiring a median of 61 months from request to operation. In August, the U.S. Department of Transportation announced the America’s Great Corridors of Commerce (AGGC) proposal that could open thousands of miles of land reserved for highways and make it multi-purpose for crucial infrastructure.
- The opportunity: Thousands of miles of highway rights-of-way (ROW) managed by State Departments of Transportation could accommodate new power and communications infrastructure, with implications for grid access, energy optimization, and national security. Yet 44 states undercharge for ROW access, 36 ban parallel transmission lines, and no national map tracks what lies above or below 200,000 miles of federal and state highways.
- Problem solving: The Build America Bureau’s America’s Great Corridors of Commerce (AGCC) proposal creates an opportunity to nationally scale utility colocation in highway ROW, backed by comprehensive asset inventories, standardized valuation frameworks, and multi-utility corridors that bypass greenfield bottlenecks.
Rights-of-Way as a hidden asset
A ROW is land owned, acquired, or reserved by a transportation authority for the construction and long-term operation of a highway. Highway ROW can include shoulders, medians, buffers and roadside strips of land, including land that has often been altered by construction, though existing approvals do not automatically authorize new utility construction. Ownership also matters: a state DOT may own the land outright or hold only an easement that limits its use. Even outright ownership does not always confer authority to collect revenue from utilities.
Wisconsin is a good working example of utility colocation on highway ROW. In 2003, the state passed legislation that allowed transmission lines to be built on vacant strips of land within highway ROW. A cooperative agreement between WisDOT and the state Public Service Commission guided coordination, providing a working model for collocating utilities. Since then, Wisconsin has permitted more than 200 miles of transmission across 26 projects in highway corridors, eight of them in Interstate rights-of-way.
The best-known result is the 180-mile, 345-kilovolt Badger-Coulee transmission line, which follows the ROW of Interstates 90 and 94 for approximately 100 miles. Siting the line along the highway avoided 300-400 private easements compared with a greenfield route. The project took 8.5 years from conception to operation, while major transmission projects can take a decade or more. The American Great Corridors of Commerce proposal aims to extend that idea nationally, with states and private partners co-locating utilities such as fiber, water and electric transmission in public right-of-way.
While fiber and broadband already use highway ROW, 44 states charge such utilities only enough to cover administrative costs, not what the land is worth; and six have no valuation method at all. Pricing is only part of the problem. Existing maps do not show what is above or below ground, how much space remains available for utilities, or what infrastructure needs a corridor could realistically serve. This reflects a familiar problem in public asset management where governments know their debts better than their assets. Simply knowing what lies underground reduces project costs by $4.62 for every $1 spent on subsurface utility engineering. With demand for power and connectivity rising, that unmeasured land is becoming a strategic route for new infrastructure. Three pressures build the case for colocation – grid access, energy optimization and national security.
Grid Access
With U.S. electricity demand projected to grow substantially, the current 61-month median time from interconnection request to operation is nearly triple the 22 months it took in 2008. Equipment is also a constraint. Existing corridors can shorten siting timelines, and Badger Coulee indicates fewer of the landowner conflicts that stall greenfield lines. However, colocation by itself does not resolve interconnection backlogs or equipment shortages. To translate that siting advantage into faster grid access, DOTs should work with utilities and regional grid planners to identify corridors where new lines could relieve congestion or connect generation to demand.
Energy optimization
Colocation is also a competitiveness question. China laid at least 8,200 miles of ultra-high-voltage lines early this decade, compared with just 375 miles in the United States, a ratio of roughly 22 to 1. Meanwhile, only 3% of transmission upgrades in the Southwest Power Pool (SPP) and the Midcontinent Independent System Operator (MISO) markets between 2016-2022 crossed state lines, leaving $2 billion in allocative inefficiencies. Highway corridors already cross state lines, but a patchwork of state rules limits their use. Thirty-six states ban transmission lines from running parallel to highway ROW, ten generally permit it and four actively encourage it. A continuous highway corridor can be open to a utility on one side of a border but closed on the other. Public land can speed up grid investment at little cost to the taxpayer.
Revenue is a real but secondary benefit. For instance, Iowa DOT collects a right-of-way occupancy fee ranging from $4,000 to $13,000 per mile of cable, depending on the type of installation, with fees rising 3% annually.
Colocated corridors can also support transportation digital infrastructure (TDI), which integrates physical infrastructure, digital systems, computing resources and energy for safe, secure transportation. The U.S. DOT’s 2026 request for information sought input on a national TDI strategy intended to provide a framework for the next generation of transportation across all modes. Highway ROW can help put that framework into practice by accommodating the power and fiber these systems need. Georgia DOT will operate 1,400 miles of fiber in the coming years, laying a foundation for connected, autonomous and AI applications.
National Security
A reliable, secure and affordable grid is directly tied to U.S. defense readiness. The Department of War is the largest energy consumer in the federal government, and 750 active duty and reserve installations across the U.S. depend on civilian grids. Meanwhile, strategic competitors like China treat grid capacity as a direct extension of their national strategy.
Adversaries are already probing this infrastructure. In 2024, the Cybersecurity and Infrastructure Security Agency (CISA) reported that Volt Typhoon, a China-sponsored hacking group, had compromised U.S. networks in communications, water, energy and transportation, positioning itself to disrupt essential services during a crisis. At the same time, a corridor that carries power, communications and autonomous logistics together could expose all three to the same physical or digital disruption and would require security to be built into procurement from the outset.
What comes next
The Build America Bureau’s proposed America’s Great Corridors of Commerce (AGCC) initiative seeks to expand shared use of existing highway and railroad ROW for transmission, fiber and other utilities. In the comments that SAFE’s Coalition for Reimagined Mobility (ReMo) submitted in October, we supported the initiative and urged DOT to make energy optimization, secure grid access and resilience central to its design.
This approach builds on our AI in Motion (2025) research, which identified three barriers to smarter, safer transportation. The first is infrastructure, specifically electricity, computing power and chips. The second is a patchwork of state rules. The third is a growing standards race with China.
A collocated corridor can help address all three. Corridors cannot make chips but can bring power and fiber, the physical foundation for compute, to the locations where autonomous and AI-enabled transportation needs computing capacity. Federal guidance can help states align their utility accommodation policies, and a shared technical reference architecture can establish common requirements for interoperability and security.
To help put AGCC into practice, the U.S. DOT should work with states and private partners to inventory ROW assets, develop consistent valuation guidance, and launch a small number of viable pilot corridors. As ReMo recommended in its comments, these projects should align with utility planning and incorporate cybersecurity, supply chain security and resilience into corridor design and procurement. Pilots can establish practices that can be applied across states as the initiative expands.
These early investments matter because whoever builds the shared backbone first will shape the rules for the next generation of American mobility.